国产视频99丨亚洲男生自慰xnxx丨国产又粗又猛又爽的视频a片丨欧美激情首页丨亚洲男人影院丨久久亚洲精品情侣丨一区二区小视频丨精品久久久久久久无码人妻热丨一个色综合久久丨国产成人精品日本亚洲77上位丨av有码在线观看丨美女一区二区三区四区丨国内精品一区二区三区不卡丨中文在线无码高潮潮喷在线播放丨少妇性bbb搡bbb爽爽爽欧美丨日本免费一区二区三区最新vr丨人人爱人人射丨九九热国产视频丨艳妇臀荡乳欲伦交换在线看丨男女视频国产

Position: 首頁 < Home < Outstanding Cases

CHN ENEGRY JIANGSU GUOMAO BIPV&BAPV EPC PROJECT

4-1.jpg

The full name of the project is 40.013MW PV EPC Project of Guoneng Jiangsu New Energy Technology Development Co.

Wuhan Institute of Building Materials (WIBI) has successfully realized the grid connection of 40MWp photovoltaic power plant project of Guoneng New Energy Company in Wujin. This project is the largest single distributed PV project of Guoneng Jiangsu New Energy Company, which was officially started on June 30th this year, with a contract duration of 180 days. Under the joint efforts of all parties, the project department strictly ensured the safety and quality, and realized the full-capacity grid-connection one month ahead of schedule.


?